Main Roads Update – Friday 6 September 2013

Friday 6 September 2013

TOWNSVILLE

13 19 40 Traffic and Travel Information – Disaster recovery TMR – Facebook TMR

Click here for printer friendly version

All dates are subject to weather

Burdekin Shire

Bruce Highway (Bowen – Ayr)
South of Homestead Road and Charlie’s Hill Road
Overtaking lanes
Anticipated completion: November 2013
  • The construction of the new overtaking lane south of Homestead Road and Charlie’s Hill Road is progressing well and still on track to finish in November
  • The Bruce Highway through this project has been reduced to single lane operation with traffic signals managing the flow of traffic.  Minor delays can be expected, speed and width restrictions are in place
  • Advanced warning signs are also in place to notify road users of these changes.  Motorists are urged to slow down, be patient and obey all signage when travelling through this project

Community Engagement Officer – Kelly Stolz

More…

Bruce Highway (Bowen – Ayr)
Seventh Avenue
Reconstruction works
Anticipated completion – late October 2013
  • Natural Disaster Relief and Recovery Arrangements works along Seventh Avenue, from Fifteenth Street to the Inkerman Mill tram line, Home Hill, are still on track for completion in October 2013
  • Motorists are strongly urged to heed traffic controllers’ instructions and abide all speed restrictions whilst travelling through this project.  Traffic signals will be in operation after hours and delays of up to 15 minutes can be expected
  • All excess dimension loads wider than 3.5 metres are to contact Chris MacDonald on 0429 413 912 prior to passing through the roadworks, with notice to be provided a minimum of 48 hours in advance

Community Engagement Officer – Steven MacDonald

More…

Bruce Highway (Bowen – Ayr)
Rossiter’s Hill
Overtaking lanes
Anticipated completion: November 2013
  • The construction of this new southbound overtaking lane, south of Rossiter’s Hill, is well underway
  • This project is between Home Hill and Ayr, just north of the Giddy Road and McDesme Road intersection
  • Motorists can expect minor delays, lane closures and width and speed restrictions
  • Advanced warning signs have been erected to notify road users of these changes and motorists are urged to slow down, be patient and obey all signage when travelling through this project

Community Engagement Officer – Kelly Stolz

More…

Bruce Highway (Ayr-Townsville)
Sandy Corner to Collinson’s Lagoon
Road realignment
Anticipated completion – mid 2014
  • The southbound overtaking lanes located to the north side of the project is nearing completion, with minor works and the final layers of asphalt to be applied.  This is a significant milestone for the project team and a vast improvement for all motorists
  • Hoey Road will be closed to all traffic commencing 23 September 2013 and will reopen 14 October 2013.  Please seek an alternative route if you need to travel along Hoey Road
  • Speed restrictions will remain a priority for the project site, these are in place for the safety of all motorists and our workers.  TMR asks all motorists to adhere to these restrictions as Queensland Police regularly patrol this section of the highway

Community Engagement Officer – Steven MacDonald

More…

Bruce Highway (Ayr-Townsville)
Pink Lily Lagoon
Reconstruction works
Anticipated completion – October 2013
  • Natural Disaster Relief and Recovery Arrangements works at Pink Lily Lagoon just north of the Haughton River Bridge are progressing well
  • Width Restrictions – All excess dimension loads wider than 3.5m are to contact Steve Coulter on 040 8066 443 or Chris MacDonald on 0429 413 912 a minimum of 24 hours prior to passing through the roadworks
  • Motorists are asked to obey traffic controllers’ instructions and signage whilst driving through the project site
  • Expected completion of these works is late October 2013

Community Engagement Officer – Steven MacDonald

More…

Woodstock-Giru Road
Woodstock-Giru Road
Reconstruction works
Anticipated completion – December 2013
  • Works are well underway for the Natural Disaster Relief and Recovery Arrangements works along the Woodstock-Giru Road
  • The works are concentrated between the Bruce Highway/Woodstock Giru Road intersection and Geary’s Road
  • Culvert works are continuing throughout the site and stabilisation of prepared overlay has also commenced
  • For the duration of the project, motorists can expect delays of about 10-15 minutes due to lane closures and speed restrictions
  • Wide loads restrictions of more than 3.5m are also in place and are directed to contact John Cash on 0429 066 350 or Daniel Kennedy on 0407 157 785 prior to passing through the roadworks, with notice to be provided a minimum of 48 hours in advance

Community Engagement Officer – Steven MacDonald

More…

Townsville City

Garbutt – Upper Ross Road
Dalrymple Road / Banfield Drive / Angus Avenue intersection
Drainage works
Anticipated completion – December 2013
  • Drainage works have commenced along Angus Avenue, between the Dalrymple Road / Banfield Drive intersection and Dalrymple Service Road, Heatley
  • As part of these works, TMR will need to temporarily close this section of Angus Avenue for approximately three weeks from Monday 23 September 2013
  • At this time, no lane closures are expected along Dalrymple Road however speed restrictions will be implemented
  • Advanced warning signs will also be erected when the closure is implemented and TMR requests motorists to seek alternative routes during this period

Community Engagement Officer – Paula Paoletti

More…

Bruce Highway (Townsville – Ingham)
Rollingstone
Reconstruction works
Anticipated completion – early October 2013
  • Natural Disaster Relief and Recovery Arrangements work along the Bruce Highway at the Rollingstone Weigh Pad just north of the Rollingstone Road are now in full swing
  • Traffic controllers and speed restrictions are in place during the day with traffic signals in operation after hours.  Motorists can expect delays of up to 15 minutes
  • Wide loads of more than 3.5m are directed to contact Brett Hearn on 0408 751 859 or Chris MacDonald 0429 413 912 prior to passing through the roadworks, with notice to be provided a minimum of 48 hours in advance

Community Engagement Officer – Steven MacDonald

More…

Hervey’s Range Developmental Road (Townsville-Battery)
Hervey’s Range Road
Reconstruction works
Anticipated completion – February 2014
  • Natural Disaster Relief and Recovery Arrangements work along 24kms of the Hervey’s Range Road are well underway
  • Hervey’s Range Road will be subject to changed traffic conditions.  This will include lane closures, side tracks, width and speed restrictions. As a result, motorists can expect delays of up to 15 minutes
  • Motorists are advised to observe and obey all signage when travelling through this project
  • Wide loads must contact the site supervisor Rob White 0429 434 759 or Peter Webster 0408 135 348 prior to arriving so that arrangements can be made to ensure safe passage through the worksite

Community Engagement Officer – Steven MacDonald

More…

Hinchinbrook Shire

Bruce Highway (Ingham-Innisfail)
Hawkins Creek to Arnot Creek
Reconstruction works
Anticipated completion – late September 2013
  • Natural Disaster Relief and Recovery work between Hawkins Creek North and the Arnot Creek, north of Ingham, is progressing with four sections under construction
  • Full width pavement rehabilitation works will continue at Hawkins Creek and concrete floodway work at the Seymour River Bridge.
  • Heavy vehicle operators are reminded that excess dimension loads wider than 3m are to contact 1. Shane Cairncross 0409 843 158, 2. Russell Nielsen 0400 577 675 or 3. Les Wilson 0488 001 117 a minimum of 24 hours prior to passing through the roadworks
  • Speed restrictions and single lane closures with delays of up to 15 minutes will be in place for the duration of the works

Community Engagement Officer – Steven MacDonald

More…

Bruce Highway (Ingham-Innisfail)
Arnot Creek Bridge
Speed restrictions
  • The Arnot Creek Bridge is open to two lanes of traffic, however a 60km/hr speed limit over the bridge remains in place until bridge repairs have been investigated and completed
  • Motorists are advised to observe and obey all signage when travelling through this site

Community Engagement Officer – Steven MacDonald

More…

Bruce Highway (Ingham-Innisfail)
Cardwell Range Realignment
Anticipated completion – November 2013
  • Work on realigning the Bruce Highway through the Cardwell Range to improve safety and traffic flow is continuing and with weather permitting, will be completed by November 2013
  • Intermittent lane closures for the remainder of the works can be expected
  • Major crest cutting work on the northern end of the range is continuing
  • Road restrictions are in place, all wide loads greater than 3.5m are required to contact Adrian Van Aredonk or his delegate on 0410 463 065 no less than 48 Hours prior to passing through this project
  • The Cardwell Range Alliance reserves the right to restrict access to any vehicles not complying with these conditionsCommunity Engagement Officer – Steven MacDonald

More…

Charters Towers Shire

Flinders Highway (Townsville – Charters Towers)
Cardington Road to Oakey Creek
Reconstruction works
Anticipated completion:  late October 2013
  • Approximately 10kms of work between Cardington Road and Oakey Creek have commenced and is being delivered under the Natural Disaster Relief and Recovery Arrangements (NDRRA)
  • As a result of the works, the Flinders Highway will be subject to changed traffic conditions.  This will include lane closures, side tracks, width and speed restrictions
  • Advanced warning signs will be used to notify road users of these changes
  • When work commences, motorists are advised to observe and obey all signage when travelling through this project

Community Engagement Officer – Steven MacDonald

More…

Flinders Highway (Charters Towers – Hughenden)
Traveller Information Board to Alpha Creek
Reconstruction works
Commencing soon – anticipated completion February 2014
  • Work over several sections of the Flinders Highway between the Traveller Information Board and Alpha Creek, to be delivered under the Natural Disaster Relief and Recovery Arrangements (NDRRA), is due to commence next week
  • For the duration of these works, the Flinders Highway will be subject to changed traffic conditions which will include lane closures and speed restrictions with delays of up to 15 minutes
  • Excess dimension restrictions will also be in place for loads wider than 3.5 metres.  Operators must contact Tony Catton on 0418 490 894 prior to passing through the roadworks, with notice to be provided a minimum of 48 hours in advance
  • When work commences, motorists are urged to observe and obey all signage when travelling through this project

Community Engagement Officer – Steven MacDonald

More…

Flinders Highway (Charters Towers – Hughenden)
Granite Creek Bridge
Changed conditions
  • Due to changes with the Department of Transport and Main Roads’ (TMR) structural standards and for motorists’ safety, the Granite Creek Bridge, 92 km south west of Charters Towers has been reduced down to one lane
  • In addition, a 60km/hr speed limit has been put in place
  • These measures have been taken as a precaution until bridge strengthening works can take place
  • Motorists have been advised to observe and obey all signage when travelling over this bridge

Community Engagement Officer – Paula Paoletti

More…

Gregory Developmental Road (Belyando-Charters Towers)
Victoria Creek and Policeman Creek
Reconstruction works
Anticipated completion – November 2013
  • The Natural Disaster Relief and Recovery Arrangements work is continuing along the Gregory Developmental Road, between Victoria Creek and Policeman Creek
  • Work is progressing well along this stretch of road.  Motorists can still expect single lane closures with delays of up to 15 minutes
  • All Excess dimension loads wider than 3.5m shall contact Brett Harding on 0407 646 538 prior to passing through the roadworks, with notice to be provided a minimum of 24 hours in advance
  • Please note reconstruction work is also being conducted about 13kms south of this project (refer item below)

Community Engagement Officer – Paula Paoletti

More…

Gregory Developmental Road (Belyando-Charters Towers)
Pajingo Station
Reconstruction works
Anticipated completion – early October 2013
  • About 4kms of roadworks near the Pajingo Station along the Gregory Developmental Road is progressing well
  • Traffic controllers and speed restrictions are in place for the duration of the works and delays of up to 10 minutes can be expected.  Traffic signals will be in operation after hours
  • All excess dimension loads wider than 3.5m are to contact Brett Harding on 0407 646 538 prior to passing through the roadworks, with notice to be provided a minimum of 24 hours in advance
  • Please note reconstruction work is also being conducted about 13kms north of this project (refer above item)

Community Engagement Officer – Paula Paoletti

More…

Gregory Developmental Road (Charters Towers-Lynd)
Hervey’s Range Road and north of Stockyard Creek floodway
Reconstruction work
Anticipated completion – March 2014
  • Natural Disaster Relief and Recovery Arrangements work along the Gregory Developmental Road between Hervey’s Range Road and just north of Stockyard Creek floodway is moving along quite well
  • Stablisation works nearing completion prior to work crews moving onto the next section of the project
  • Speed restrictions are in place, however no additional mass restrictions will apply
  • Traffic controllers are also in place for the duration of the works and delays of up to 10 minutes can be expected.  Traffic signals will be in operation after hours
  • All Excess dimension loads wider than 3.5m are to contact either the site office on 4788 5091 or Jesse Palk on 0427 469 946 or Stevie Hughes 0407 159 920 or Warren Preston 0439 898 334 prior to passing through the roadworks, with notice to be provided a minimum of 24 hours in advance

Community Engagement Officer – Steven MacDonald

More…

Planning your trips

Please plan for extra time when travelling

All roadwork schedules and timelines are weather permitting and are subject to change

Motorists are encouraged to slow down and drive to the conditions of the road. This will allow work crews to complete their work quickly and safely

For more information about these works,
please contact your community engagement officer
Freecall: 1800 625 648*
or email

For up-to-date information on traffic disruptions, please phone 13 19 40
or visit www.131940.qld.gov.au

*free call from anywhere in Australia.  Call charges apply for calls from mobile phones and payphones.

 

Comments are closed.