Temporary Closure – Plantation Creek Boat Ramp

The Department of Transport and Main Roads (TMR) will be upgrading the Planation Creek western boat ramp located at 652 Old Wharf Road, Airdmillan.

The project will:

  • replace the existing boat ramp with new pre-cast concrete planks
  • increase the two-lane boat ramp from seven metres wide to the standard eight metres wide
  • extend the length of the ramp from 20.5 metres to 34.4 metres long
  • carry out additional earthworks and rock protection works.

Construction is scheduled to commence on Monday 16 April 2018 and is expected to be completed by 30 June 2018, weather permitting.

Access to the western ramp will be closed during construction so that work can be completed safely and efficiently.  The eastern ramp and pontoon will remain open.

More information about the located and details of the Plantation Creek boat ramp upgrade can be found here TMR Temporary Boat Ramp Closure.

Further information about the Plantation Creek boat ramp project can be obtained by contacting TMR’s Customer and Stakeholder Management team on 1800 625 648 or via email at .